Solar Projects


STATUS OF DIFFERENT SOLAR PROJECTS OF WBSEDCL AS ON 31.12.2019

Sl. No. Type of Project Name of the Project Present Status Remarks
1
Rooftop Grid Connected Solar PV Power Plant 100 Schools ( 10 KWp capacity each) Grid-connected Solar Roof top Programme of WBREDA Project Completed. 92 nos. of already installed and running successfully. O & M work is being maintained by the Agencies for the 5 years. Later WBREDA took up the work and rest of the schools had been completed by them. Total Cumulative Generation as on 31.12.2019 is about 4.560 MU.
2
200 Schools ( 10 KWp capacity each) Grid-connected Solar Roof top Programme of WBSEDCL Plants already commissioned - 140 nos Project Completed. Plants already commissioned - 140 nos.. 140 nos. of school installation work completed as per fund sanctioned by the State Government. Due to non availability of fund from MNRE, Project stopped at 140 nos. and already intimated to WBREDA.
3
5.285 MW Rooftop Solar PV Plant (5 kWp each) Project under IPDS Programme LOA has been placed for all 19 no of packages and work is under progress. Out of 5.285 MW Solar Projects under IPDS, 3.715 MW was found suitable for the Solar Project and rest was not suitable for the Solar Project due to some technical problems. Survey of 3.715 MW completed in our WBSEDCL / WBSETCL buildings. In which, 3.675 MW capacity has already been installed & commissioned as on 31.12.2019. Target date of completion: Dec. 2019.
4
10.5 MW Rooftop Solar PV Plant (Min. 10 kWp each) Project under Alo Shree Programme LOA has been placed for all 5 nos. of packages and work is under progress. Out of 10.5 MW Solar Projects under Aloshree, 5.250 MW was found suitable for the Solar Project and rest was not suitable for the Solar Project due to some technical problems. Survey of 5.250 MW completed in our WBSEDCL / WBSETCL buildings. In which, 3.98 MW capacity has already been installed & commissioned as on 31.12.2019. Target date of completion : Dec 2019
5
Ground Mounted Grid Connected Solar PV Power Plant 10 MW Teesta Canal Bank Solar PV Power Project Project Completed Project commissioned on 18.08.2016 and now running in full capacity. Total Cumulative Generation as on 31.12.2019 is about 44.309711 MU.
6
10 MW Solar PV Project at Mejia, Bankura Project Completed 10 MW commissioned on 15.12.2017 and now running in full capacity. Total Cumulative Generation as on 31.12.2019 is about 15.290416 MU.
7
10 MW Solar PV Project at Charrah, Purulia Project Completed 10 MW commissioned on 15.12. 2018. Total Cumulative Generation as on 31.12.2019 is about 13.5249482 MU.
8
10 MW Solar PV Project at Santaldih, Purulia Some tit bit civil works are going on. 10 MW commissioned as on 30.09.2019. Recently due to some Local problems, Solar Plant has been kept in off condition.
9
10 MW Solar PV Project at Khemasuli (Patni), Paschim Medinipur. Project completed 10 MW commissioned on 03.01.2019. Total Cumulative Generation as on 31.12.2019 is about 13.7570 MU.
10
10 MW Solar PV Project at Salboni, Paschim Medinipur Project completed. 10 MW commissioned on 27.12.2018. Total Cumulative Generation as on 31.12.2019 is about 14.49383 MU
11
10 MW Solar PV power plants on canal top of TCFHP Tail Race Canal, Stage II Power Station at Haptiagachh in Uttar Dinajpur District. Project completed. 10 MW commissioned on 28.08.2019 and now running in full capacity. Total Cumulative Generation as on 31.12.2019 is about 4.35763 MU.
12
10 MW Solar PV Project at Chalbalpur Raniganj, Burdwan Work is under progress. Expected to be commissioned: March 2020
13
10 MW SPV Project at Dhaka - I at Birbhum, West Bengal Work is under progress. Expected to be commissioned: March 2020
14
10 MW SPV Project at Dhaka - II at Birbhum, West Bengal Work is under progress. Expected to be commissioned: March 2020
15
Ground Mounted Grid Connected Solar PV Power Plant 10 MW Solar PV Project at Koltaldih (Phase - I), Asansol, Burdwan district Work is under progress. Demarcation of Land has been completed by the Agency with the help of respective BL&LRO Officials and work is under progress. Expected to be commissioned: August 2020.
16
10 MW Solar PV Project at Srirampur, Jhargram, Paschim Medinipur district Tendering process has already been completed LOA not placed due to non availability of land. The said land is under possession of forest Department. An alternate land has been identified at Sankrail Block, Jhargram. Availability report of land has been received from the respective BL&LRO. Re tender is in process.
17
06 MW Solar PV Power Project at Atna Due to land dispute, 5 nos. Solar Projects surrendered to NABRAD vide letter no. 951-F.B. dated 21.10.2019 of Joint Secretary to the Govt. of West Bengal, Finance Department, Budget Branch.
18
10 MW Solar PV Power Plant at Kadlagora, Manbazar Block - I of Purulia district
19
03 MW Solar PV Project at Leusipukuri, Darjeeling district
20
10 MW Solar PV Project at Andherijhari, Uttar Dinajpur district
21
10 MW Solar PV Project at Koltaldih (Phase - II), Asansol, Burdwan district
22
10 MW Solar PV Power Plant at Kalpani-Baldiahati at Coochbehar District DPR has been submitted to the Power & NES Dept. GoWB for sanction under RIDF scheme of NABARD. Approval is awaited from Dept. Of Power, NES, Govt. Of West Bengal.
23
06 MW Solar PV Power Plant at Hariharpur, Purulia
24
04 MW Solar PV Project at Koltaldih (Phase - IA), Asansol, Burdwan district
25
Ground Mounted Grid Connected Canal Top Solar PV Power Plant 10 MW Solar PV Power Plants at Mahananda Main Canal, Uttar Dinajpur
26 Solar Park 200 MW Solar Park, at Dadanpatra, Purba Medinipur Detailed Project Report i.r.o . Phase - I (125 MW) & phase - II (75 MW) of 200 MW Solar Park, at Dadanpatra, Purba Medinipur has been prepared and submitted to Power Department. GoWB. MNRE, GOI has approved 125 MW (Phase - I of 200 MW) on 13.08.2019 towards taking up the execution work of Solar Park. In principal clearance has been received from Department of Economic Affairs (DEA) for drawal of loan from KFW.