Back to Top

DEENDAYAL UPADHYAYA GRAM JYOTI YOJANA (DDUGJY)

Background

Govt. of India, vide Office Memorandum F.No.44/44/2014-RE dated 3rd December 2014 issued by the Ministry of Power, launched Deendayal Upadhyaya Gram Yyoti Yojana (DDUGJY) with the following components

  1. Separation of agriculture and non-agriculture feeders for supply to agricultural & non-agricultural consumers in the rural areas for effective demand side management.
  2. Strengthening and augmentation of sub-transmission & distribution (ST&D) infrastructure in rural areas, including metering at distribution transformers, feeders and consumer end.
  3. Rural electrification, as per CCEA approval dated 01.08.2013 for completion of the targets laid down under RGGVY for 12th and 13th plans.

Board Objective of the Scheme

     Providing access to power for all households.

     24X7 Power

     AT&C loss reduction as per trajectory finalized by MoP.

Scope of Works specific to achivements of the broad objectives:

Access to Power for all households :

Electrifiction of un electrified(UE) villages and creation of new village infrastructures for access to power for all house holds


24X7 power supply for non-Agri-consumer and adequate supply for Agri-consumer :

Physical seperation of HT feeders for Agricultural and non-Agricultural consumers.


AT&C loss reduction :

Strengthening of sub-transmission & distribution sysytem and metering at all levels of distribution network.


Sailent Features of the Scheme :

Nodal Agency :    Rural Electrification Corporaion Limited(REC) is the Nodal Agency operationalisation and implementation of the scheme under the overall guidance of MoP.

Project Management Agency (PMA) :    REC Power Distribution Company Ltd(RECPDCL)and PFC Consulting Ltd(PFCCL) have been appointed as Project Management Agency(PMA)to assist in project management as well as timely implementation of the project.

Mode of Implementation :    The projects shall be implemented on turn-key basis.However some work will be executed on partial turnkey/departmental basis for which approval has been received from the Monitoring Commitee,MoP,GOI.

Implementation Period :    Projects under the scheme shall be completed within a period of 24 months from the date of issue of Letter of Award (LoA). For execution of work on partial turnkey/departmental basis, project needs to be completed within 30 months from date of communication of the approval of the Monitoring committee.

Funding pattern of the Scheme :


Agency Nature of Support Quantum of support
(Percentage of Project Cost)
Govt.of India Grant 60%
State Contribution Grant 25%
WBSEDCL own Contribution/Loan Own
contribution/Loan
15%


Approval of the Project by Nodal Agency:
The component wise cost as per district wise submitted DPRs were approved in the 6th Monitoring commitee held on 10/12/2015 and comminucated by the Nodal Agency The REC Ltd.vide memo no:REC/ZO/KOL/DDUGJY/2015-16/834 Dated 01/02/2016

Component wise Sanctioned cost :


Sl.No Items Cost
(Rs in Crore)
1 Electrification of Un electrified villages. 46.86
2 Sansad Adarsh Gram Yojana (SAGY) 0.60
3 Metering 441.22
4 Feeder Separation 1159.96
5 Access to rural Households 1729.93
6 System Strengthening 862.34
  Total Project Cost: 4240.90
7 PMA Charges @0.5% of total project cost 21.20
  Total Sanctioned project cost 4262.10
8 PMA Charges @1% of total Project cost (Borne by WBSEDCL) 42.40
  Total Project Cost : 4304.50


DPR wise sanctioned cost Under the Project

SlNo. Name of District Elect of UE Villages SAGY Metering Access to rural HH System Strength enling Feeder Separation Total Financial Involvement
(Rs.in Crores)
1 Bankura Nil Nil 19.99 102.03 35.77 68.12 225.91
2 Bardhaman Nil Nil 28.47 141.43 75.17 145.63 390.7
3 Birbhum Nil Nil 26.55 96.31 46.58 117.45 286.89
4 Dakshin
Dinajpur
Nil Nil 14.07 58.27 33.53 34.88 140.75
5 Darjeeling Nil 0.6 8.72 47.63 45.23 9.82 112
6 Howrah Nil Nil 24.65 46.3 45.41 5.24 121.6
7 Hoghly Nil Nil 20.52 148.43 24.89 72.9 266.74
8 Jalpaiguri Nil Nil 9.99 55.1 53.71 16.28 135.08
9 Coochbehar Nil Nil 11.62 41.85 45.75 3.72 102.94
10 Malda Nil Nil 36.51 50.72 81.44 92.37 261.04
11 Mursidabad Nil Nil 26.19 103.84 46.12 117.9 294.05
12 Nadia Nil Nil 24.57 105.47 49.81 88.2 268.05
13 North 24
Parganas
Nil Nil 39.01 152.11 46.82 67.65 305.58
14 North 24
Parganas(Bidhannagar)
Nil Nil 6.03 11.89 2.3 4.15 24.36
15 Paschim
Midnapore
Nil Nil 44.77 175.71 62.47 180.99 463.94
16 Purba
Midnapore
Nil Nil 37.14 99.01 58.12 55.51 249.78
17 Purulia Nil Nil 15.08 67.39 15.05 7 104.51
18 South 24
Parganas
46.86 Nil 33.18 170.26 50.71 43.51 344.51
19 Uttar
Dinajpur
Nil Nil 14.16 56.19 43.47 28.66 142.47
  Total 46.86 0.6 441.22 1729.93 862.34 1159.96 4240.90


DETAIL SCOPE OF WORK UNDER DEENDAYAL UPADHYAYA GRAM JYOTI YOJANA (DDUGJY)


Sl No DETAIL SCOPE OF WORK UNIT QUANTITY FInancial Involvement
(Rs in lakhs)
I ELECTRIFICATION OF UE VILLAGES
(14 no villages in Gosaba,Namkhana & Patharpratima Block under south 24 Pargana District)
     
a) Installation of new DTR No 294 46.86
b) Drawal of new 11KV Spur Line DTR KM 165
c) Drawal of new LT AB Cable KM 530
d) Connection to BPL House Holds No 6,790
         
II FEEDER SEPARATION :
(Physical Separation of HT Feeders for Agricultural & Non Agricultural Consumers)
     
a) New 11KV Bay NO 461 875.76
b) New 11KV Line (621 no feeder) KM 12464
c) Installation of new DTR NO 8573
         
III ACCESS TO RURAL HOUSEHOLDS
(for connecting unconnected households)
     
a) Capacity Augmentation of existing DTR No 3457 1712.87
b) Conversion of existing LT O.H. Line to AB Cable KM 28287.149
c) Installation of new DTR NO 10354
d) New 11KV Spur Line KM 2268.198
e) New LT AB Cable line KM 1328.95
f) New LT O.H Line KM 1084.709
g) Connection of BPL HHs NO 24515
         
(IV) METERING      
a) Installation of Dist Transformer metering NO 27718 319.93
b) Installation of FEEDER Metering NO 512
c) Replacement of defective /electro magnetic(old)consumer Metering NO 1896241
d) Shifting of existing consumer metering NO 414045
         
(V) SANSAD ADARSH GRAM YAJONA      
a) Installation of new 11 KV Bay NO 1 0.51
b) Drawal of new 11KV Line KM 4.2
       
(VI) SYSTEM STRENGTHENING      
a) Drawal of new New 33KV Line KM 1625.2 748.74
b) Augmentation of existing 33 KV Line KM 82
c) Construction of New 33/11KV Sub Station NO 80
d) Augmentation of existing 33/11KV Sub Stations NO 106
e) Drawal of New 11KV Line KM 991
f) Augmentation/Renovation of existing 11KV Line KM 1,926
g) Installation of new 33KV Bay NO 77
         
  GRAND TOTAL:     3704.67




UP-TO-DATE STATUS OF DDUGJY SCHEME AS ON 31.07.2021

A . Status of Work Village Infrastructure for access to power for all Rural Household ,Feeder Separation and Metering work in Turnkey Mode as on 31.07.2021

SL NO: District Item of Work Status of Award/Tender Name of Awarded Turnkey Agencies Staus of work Target for completion
1 North 24 parganas Feeder Segregation LOA Issued M/S L&T Ltd 33 no Feeders are commissioned out of 33 no. feeders. Completed
Metering 1,97,805 no. defective consumer meters replaced out of 1,97,805 no. in scope.
Village Infrastructure for access to power for all Rural HH. 3,067 km renovation of LT line by AB Cable completed out of 3,067 km in scope.
1,569 no New Distribution Transformer installed out of 1,569 no. in scope.
2 South 24 parganas and Biddhannagar Feeder Segregation LOA issued M/S IL&FS ECC Ltd 10 no Feeders are commissioned out of 10 no. feeders. December,2021
Metering 2,41,492 no. defective consumer meters replaced out of 2,41,492 no. in scope.
Village Infrastructure for access to power for all Rural HH. 2,038 km renovation of LT line by AB Cable completed out of 2,038 km in scope.
700 no New Distribution Transformer installed out of 726 no. in scope. 368 no. augmentation of DTR completed out of 368 no. in scope.
Electrification of 14 UE & 59 PE villages in Sundarban area. LOA issued M/S Sterling & Wilson Ltd Work Completed Completed
3 Howrah Feeder Segregation LOA Issued M/S Sterling and Wilson Pvt. Ltd 05 no Feeders is commissioned out of 06 no. feeders. December,2021
Metering 2,10,507 no. defective consumer meters replaced out of 2,13,857 no. in scope.
Village Infrastructure for access to power for all Rural HH. 730 km renovation of LT line by AB Cable completed out of 730 km in scope.
287 no New Distribution Transformer installed out of 313 no. in scope.
4 Burdwan Feeder Segregation LOA issued M/S Lumino Ind. Ltd 90 no Feeders are commissioned out of 91 no. feeders.
1,466 no New Distribution Transformer installed out of 1,466 no. in scope.
September,2021
Metering LOA issued M/S NCC Ltd 1,49,964 no. defective consumer meters replaced out of 1,49,964 no. in scope.
Village Infrastructure for access to power for all Rural HH. LOA issued 3,654 km renovation of LT line by AB Cable completed out of 3,654 km in scope.
955 no New Distribution Transformer installed out of 955 no. in scope.
5 Hooghly Feeder Segregation LOA issued M/S L&T Ltd 31 no Feeders are commissioned out of 31 no. feeders. Completed
Metering 1,53,720 no. defective consumer meters replaced out of 1,53,720 no. in scope.
Village Infrastructure for access to power for all Rural HH. 2,581 km renovation of LT line by AB Cable completed out of 2,581 km in scope.
1,323 no New Distribution Transformer installed out of 1,323 no. in scope.
6 Birbhum Feeder Segregation LOI Issued M/S L&T Ltd 57 no Feeders are commissioned out of 58 no. feeders. September,2021
Metering 1,14,898 no. defective consumer meters replaced out of 1,14,898 no. in scope.
Village Infrastructure for access to power for all Rural HH. 3,467 km renovation of LT line by AB Cable completed out of 3,467 km in scope.
1,223 no New Distribution Transformer installed out of 1,240 no. in scope.
7 Malda Feeder Segregation LOI issued M/S Bajaj Electricals Ltd. 23 no Feeders are commissioned out of 26 no. feeders. December,2021
Metering 1,00,017 no. defective consumer meters replaced out of 1,00,017 no. in scope.
Village Infrastructure for access to power for all Rural HH. 905 km renovation of LT line by AB Cable completed out of 905 km in scope.
1,510 no New Distribution Transformer installed out of 1,654 no. in scope. 404 no. augmentation of DTR completed out of 404 no. in scope.
8 Murshidabad Feeder Segregation LOA issued M/S SPML Ltd. 45 no Feeders are commissioned out of 50 no. feeders.
312 no New Distribution Transformer installed out of 340 no. in scope.
March,2021
Metering LOA issued M/S L&T Ltd. 1,44,898 no. defective consumer meters replaced out of 1,44,898 no. in scope.
Village Infrastructure for access to power for all Rural HH. 3,343 km renovation of LT line by AB Cable completed out of 3,343 km in scope.
338 no New Distribution Transformer installed out of 339 no. in scope. 713 no. augmentation of DTR completed out of 713 no. in scope.
9 Nadia Feeder Segregation LOA issued M/S L&T Ltd. 33 no Feeders are commissioned out of 33 no. feeders. Completed
Metering 2,04,975 no. defective consumer meters replaced out of 2,04,975 no. in scope.
Village Infrastructure for access to power for all Rural HH. 3,074 km renovation of LT line by AB Cable completed out of 3,074 km in scope.
1,114 no New Distribution Transformer installed out of 1,128 no. in scope. 243 no. augmentation of DTR completed out of 243 no. in scope.
10 Paschim Midnapur Feeder Segregation LOI Issued M/S ILFS ECC Ltd. 53 no Feeders are commissioned out of 68 no. feeders.
795 no New Distribution Transformer installed out of 1,079 no. in scope.
December,2021
Metering LOA issued M/S L&T Ltd. 1,99,915 no. defective consumer meters replaced out of 1,99,915 no. in scope. Completed
Village Infrastructure for access to power for all Rural HH. 3,890 km renovation of LT line by AB Cable completed out of 3,890 km in scope.
807 no New Distribution Transformer installed out of 807 no. in scope. 1,438 no. augmentation of DTR completed out of 1,438 no. in scope.
11 Purba Midnapur Feeder Segregation LOA issued M/S L&T Ltd. 10 no Feeders are commissioned out of 10 no. feeders. Completed
Metering 1,89,056 no. defective consumer meters replaced out of 1,89,056 no. in scope.
Village Infrastructure for access to power for all Rural HH. 2,451 km renovation of LT line by AB Cable completed out of 2,451 km in scope.
1,633 no New Distribution Transformer installed out of 1,633 no. in scope.
12 Bankura Feeder Segregation LOA Issued M/S L&T Ltd. 24 no Feeders are commissioned out of 24 no. feeders. Completed
Metering 1,04,510 no. defective consumer meters replaced out of 1,04,510 no. in scope.
Village Infrastructure for access to power for all Rural HH. 1,664 km renovation of LT line by AB Cable completed out of 1,664 km in scope.
1,326 no New Distribution Transformer installed out of 1,326 no. in scope.
13 Purulia Metering LOA Issued M/S Montecarlo Ltd. 75,978 no. defective consumer meters replaced out of 75,978 no. in scope. Completed
Village Infrastructure for access to power for all Rural HH. 1,319 km renovation of LT line by AB Cable completed out of 1,319 km in scope.
390 no New Distribution Transformer installed out of 390 no. in scope. 42 no. augmentation of DTR completed out of 42 no. in scope.
14 Darjeeling Metering Departmental Execution 25,378 no. defective consumer meters replaced out of 25,378 no. in scope. December,2021
Village Infrastructure for access to power for all Rural HH. 682 km renovation of LT line by AB Cable completed out of 682 km in scope.
304 no New Distribution Transformer installed out of 315 no. in scope.
Sansard Adarsh Gram Yojona (SAGY) Departmental Execution Work completed. Completed
15 Jaipaiguri(including Alipurduar) Feeder Segregation LOA issued M/S L&T Ltd. 05 no Feeders are commissioned out of 06 no. feeders. December,2021
Metering 1,37,790 no. defective consumer meters replaced out of 1,37,790 no. in scope.
Village Infrastructure for access to power for all Rural HH. 1,304 km renovation of LT line by AB Cable completed out of 1,304 km in scope.
554 no New Distribution Transformer installed out of 557 no. in scope.
16 Coochbehar Feeder Segregation LOA issued M/S L&T Ltd 04 no Feeders are commissioned out of 04 no. feeders. Completed
Metering 1,16,015 no. defective consumer meters replaced out of 1,16,015 no. in scope.
Village Infrastructure for access to power for all Rural HH. 1,081 km renovation of LT line by AB Cable completed out of 1,081 km in scope.
461 no New Distribution Transformer installed out of 461 no. in scope.
Electrification of Habitations less than 100 HH. M/S BISPA India Ltd Work Completed. Completed
17 Uttar Dinajpur Feeder Segregation LOA issued M/S L&T Ltd. 14 no Feeders are commissioned out of 16 no. feeders. December,2021
Metering 1,08,243 no. defective consumer meters replaced out of 1,08,243 no. in scope.
Village Infrastructure for access to power for all Rural HH. 812 km renovation of LT line by AB Cable completed out of 812 km in scope.
619 no New Distribution Transformer installed out of 642 no. in scope.
18 Dakhin Dinajpur Feeder Segregation LOA issued M/S L&T Ltd. 17 no Feeders are commissioned out of 18 no. feeders. December,2021
Metering 96,275 no. defective consumer meters replaced out of 96,275 no. in scope.
Village Infrastructure for access to power for all Rural HH. 908 km renovation of LT line by AB Cable completed out of 908 km in scope.
522 no New Distribution Transformer installed out of 527 no. in scope. 484 no. augmentation of DTR completed out of 484 no. in scope.
B . Status of New 33/11 KV Substation Under System Strengthening in DDUGJY Scheme As on 31.07.2021
SL NO: District
Departmental
Turnkey Execution
Number Status of work Target for completion Number Status of Work Name of Turnkey agency Target for completion
1 North 24 parganas 3 All Sub-Stations commissioned. Completed
--
2 South 24 parganas and Biddhannagar 4 All Sub-Stations commissioned. Completed
3 Howrah 4 All Sub-Stations commissioned. Completed
4 Burdwan 10 All substations comissioned. Completed
5 Hooghly 3 All Substation Comissioned. Completed
6 Birbhum 3 All Sub-Stations commissioned. Completed 2 All Sub-stations Comissioned. M/S Bajaj Electricals Ltd Completed
7 Malda 5 All Sub-stations Comissioned Completed 3 All Sub-stations Comissioned M/S Bajaj Electricals Ltd Completed
8 Murshidabad 4 All Sub-Stations commissioned. Completed --
9 Nadia 4 3 No Substation Comissioned. Completed
10 Purulia 1 Sub-Stn Commissioned Completed
11 Paschim Midnapur 6 All Sub-Stations Comissioned. Completed
12 Purba Midnapur 4 All Sub-Stations commissioned. Completed
13 Bankura 0 -- Completed 3 All Substations Comissioned. M/S Bajaj Electricals Ltd Completed
14 Darjeeling 2 All Sub-Stations commissioned. Completed 2 All Substations Comissioned. M/S Bajaj Electricals Ltd Completed
15 Jaipaiguri (including Alipurduar) 1 Sub-Stn Commissioned Completed 4 All Substations Comissioned. M/S Bajaj Electricals Ltd Completed
All Substations Comissioned. M/S T&T Ltd Completed
16 Coochbehar 5 All Sub-Stations commissioned. Completed --
17 Uttar Dinajpur 4 All Sub-Stations commissioned. Completed
18 Dakhin Dinajpur 1 Sub-Stn Commissioned Completed 2 All Substations Comissioned. M/S T&T Ltd Completed
C . Status of Augmentation of Existing 33/11 KV Substation in DDUGJY Scheme as on 31.07.2021

SL NO: Name of the District Departmental Execution
Scope of PTR Augmented (No) Status of work Target for completion
1 North 24 parganas 7 7 --
2 South 24 parganas and Biddhannagar 11 11 --
3 Howrah 8 8 --
4 Burdwan 11 9 Sept,2021
5 Hooghly 5 5 --
6 Birbhum 10 10 --
7 Malda 5 5 --
8 Murshidabad 13 13 --
9 Nadia 9 9 --
10 Purulia 0 0 --
11 Paschim Midnapur 10 10 --
12 Purba Midnapur 12 11 Sept,2021
13 Bankura 14 14 --
14 Darjeeling 7 7 --
15 Jaipaiguri
(including Alipurduar)
7 7 --
16 Coochbehar 6 6 --
17 Uttar Dinajpur 8 8 --
18 Dakhin Dinajpur 3 3 --