Electrifiction of un electrified(UE) villages and creation of new village infrastructures for access to power for all house holds
Physical seperation of HT feeders for Agricultural and non-Agricultural consumers.
Strengthening of sub-transmission & distribution sysytem and metering at all levels of distribution network.
Agency | Nature of Support | Quantum of support (Percentage of Project Cost) |
---|---|---|
Govt.of India | Grant | 60% |
State Contribution | Grant | 25% |
WBSEDCL own Contribution/Loan | Own contribution/Loan |
15% |
Sl.No | Items | Cost (Rs in Crore) |
---|---|---|
1 | Electrification of Un electrified villages. | 46.86 |
2 | Sansad Adarsh Gram Yojana (SAGY) | 0.60 |
3 | Metering | 441.22 |
4 | Feeder Separation | 1159.96 |
5 | Access to rural Households | 1729.93 |
6 | System Strengthening | 862.34 |
Total Project Cost: | 4240.90 | |
7 | PMA Charges @0.5% of total project cost | 21.20 |
Total Sanctioned project cost | 4262.10 | |
8 | PMA Charges @1% of total Project cost (Borne by WBSEDCL) | 42.40 |
Total Project Cost : | 4304.50 |
SlNo. | Name of District | Elect of UE Villages | SAGY | Metering | Access to rural HH | System Strength enling | Feeder Separation | Total Financial Involvement (Rs.in Crores) |
---|---|---|---|---|---|---|---|---|
1 | Bankura | Nil | Nil | 19.99 | 102.03 | 35.77 | 68.12 | 225.91 |
2 | Bardhaman | Nil | Nil | 28.47 | 141.43 | 75.17 | 145.63 | 390.7 |
3 | Birbhum | Nil | Nil | 26.55 | 96.31 | 46.58 | 117.45 | 286.89 |
4 | Dakshin Dinajpur |
Nil | Nil | 14.07 | 58.27 | 33.53 | 34.88 | 140.75 |
5 | Darjeeling | Nil | 0.6 | 8.72 | 47.63 | 45.23 | 9.82 | 112 |
6 | Howrah | Nil | Nil | 24.65 | 46.3 | 45.41 | 5.24 | 121.6 |
7 | Hoghly | Nil | Nil | 20.52 | 148.43 | 24.89 | 72.9 | 266.74 |
8 | Jalpaiguri | Nil | Nil | 9.99 | 55.1 | 53.71 | 16.28 | 135.08 |
9 | Coochbehar | Nil | Nil | 11.62 | 41.85 | 45.75 | 3.72 | 102.94 |
10 | Malda | Nil | Nil | 36.51 | 50.72 | 81.44 | 92.37 | 261.04 |
11 | Mursidabad | Nil | Nil | 26.19 | 103.84 | 46.12 | 117.9 | 294.05 |
12 | Nadia | Nil | Nil | 24.57 | 105.47 | 49.81 | 88.2 | 268.05 |
13 | North 24 Parganas |
Nil | Nil | 39.01 | 152.11 | 46.82 | 67.65 | 305.58 |
14 | North 24 Parganas(Bidhannagar) |
Nil | Nil | 6.03 | 11.89 | 2.3 | 4.15 | 24.36 |
15 | Paschim Midnapore |
Nil | Nil | 44.77 | 175.71 | 62.47 | 180.99 | 463.94 |
16 | Purba Midnapore |
Nil | Nil | 37.14 | 99.01 | 58.12 | 55.51 | 249.78 |
17 | Purulia | Nil | Nil | 15.08 | 67.39 | 15.05 | 7 | 104.51 |
18 | South 24 Parganas |
46.86 | Nil | 33.18 | 170.26 | 50.71 | 43.51 | 344.51 |
19 | Uttar Dinajpur |
Nil | Nil | 14.16 | 56.19 | 43.47 | 28.66 | 142.47 |
Total | 46.86 | 0.6 | 441.22 | 1729.93 | 862.34 | 1159.96 | 4240.90 |
Sl No | DETAIL SCOPE OF WORK | UNIT | QUANTITY | FInancial Involvement (Rs in lakhs) |
---|---|---|---|---|
I | ELECTRIFICATION OF UE VILLAGES (14 no villages in Gosaba,Namkhana & Patharpratima Block under south 24 Pargana District) |
|||
a) | Installation of new DTR | No | 294 | 46.86 |
b) | Drawal of new 11KV Spur Line DTR | KM | 165 | |
c) | Drawal of new LT AB Cable | KM | 530 | |
d) | Connection to BPL House Holds | No | 6,790 | |
II | FEEDER SEPARATION : (Physical Separation of HT Feeders for Agricultural & Non Agricultural Consumers) |
|||
a) | New 11KV Bay | NO | 461 | 875.76 |
b) | New 11KV Line (621 no feeder) | KM | 12464 | |
c) | Installation of new DTR | NO | 8573 | |
III | ACCESS TO RURAL HOUSEHOLDS (for connecting unconnected households) |
|||
a) | Capacity Augmentation of existing DTR | No | 3457 | 1712.87 |
b) | Conversion of existing LT O.H. Line to AB Cable | KM | 28287.149 | |
c) | Installation of new DTR | NO | 10354 | |
d) | New 11KV Spur Line | KM | 2268.198 | |
e) | New LT AB Cable line | KM | 1328.95 | |
f) | New LT O.H Line | KM | 1084.709 | |
g) | Connection of BPL HHs | NO | 24515 | |
(IV) | METERING | |||
a) | Installation of Dist Transformer metering | NO | 27718 | 319.93 |
b) | Installation of FEEDER Metering | NO | 512 | |
c) | Replacement of defective /electro magnetic(old)consumer Metering | NO | 1896241 | |
d) | Shifting of existing consumer metering | NO | 414045 | |
(V) | SANSAD ADARSH GRAM YAJONA | |||
a) | Installation of new 11 KV Bay | NO | 1 | 0.51 |
b) | Drawal of new 11KV Line | KM | 4.2 | |
(VI) | SYSTEM STRENGTHENING | |||
a) | Drawal of new New 33KV Line | KM | 1625.2 | 748.74 |
b) | Augmentation of existing 33 KV Line | KM | 82 | |
c) | Construction of New 33/11KV Sub Station | NO | 80 | |
d) | Augmentation of existing 33/11KV Sub Stations | NO | 106 | |
e) | Drawal of New 11KV Line | KM | 991 | |
f) | Augmentation/Renovation of existing 11KV Line | KM | 1,926 | |
g) | Installation of new 33KV Bay | NO | 77 | |
GRAND TOTAL: | 3704.67 |
SL NO: | District | Item of Work | Status of Award/Tender | Name of Awarded Turnkey Agencies | Staus of work | Target for completion |
---|---|---|---|---|---|---|
1 | North 24 parganas | Feeder Segregation | LOA Issued | M/S L&T Ltd | 33 no Feeders are commissioned out of 33 no. feeders. | Completed |
Metering | 1,97,805 no. defective consumer meters replaced out of 1,97,805 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 3,067 km renovation of LT line by AB Cable
completed out of 3,067 km in scope. | |||||
1,569 no New Distribution Transformer installed out of 1,569 no. in scope. | ||||||
2 | South 24 parganas and Biddhannagar | Feeder Segregation | LOA issued | M/S IL&FS ECC Ltd | 10 no Feeders are commissioned out of 10 no. feeders. | December,2021 |
Metering | 2,41,492 no. defective consumer meters replaced out of 2,41,492 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 2,038 km renovation of LT line by AB Cable completed out of 2,038 km in scope. | |||||
700 no New Distribution Transformer installed out of 726 no. in scope. 368 no. augmentation of DTR completed out of 368 no. in scope. | ||||||
Electrification of 14 UE & 59 PE villages in Sundarban area. | LOA issued | M/S Sterling & Wilson Ltd | Work Completed | Completed | ||
3 | Howrah | Feeder Segregation | LOA Issued | M/S Sterling and Wilson Pvt. Ltd | 05 no Feeders is commissioned out of 06 no. feeders. | December,2021 |
Metering | 2,10,507 no. defective consumer meters replaced out of 2,13,857 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 730 km renovation of LT line by AB Cable completed out of 730 km in scope. | |||||
287 no New Distribution Transformer installed out of 313 no. in scope. | ||||||
4 | Burdwan | Feeder Segregation | LOA issued | M/S Lumino Ind. Ltd | 90 no Feeders are commissioned out of 91 no.
feeders. 1,466 no New Distribution Transformer installed out of 1,466 no. in scope. |
September,2021 |
Metering | LOA issued | M/S NCC Ltd | 1,49,964 no. defective consumer meters replaced out of 1,49,964 no. in scope. | |||
Village Infrastructure for access to power for all Rural HH. | LOA issued | 3,654 km renovation of LT line by AB Cable completed out of 3,654 km in scope. | ||||
955 no New Distribution Transformer installed out of 955 no. in scope. | ||||||
5 | Hooghly | Feeder Segregation | LOA issued | M/S L&T Ltd | 31 no Feeders are commissioned out of 31 no. feeders. | Completed |
Metering | 1,53,720 no. defective consumer meters replaced out of 1,53,720 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 2,581 km renovation of LT line by AB Cable completed out of 2,581 km in scope. | |||||
1,323 no New Distribution Transformer installed out of 1,323 no. in scope. | ||||||
6 | Birbhum | Feeder Segregation | LOI Issued | M/S L&T Ltd | 57 no Feeders are commissioned out of 58 no. feeders. | September,2021 |
Metering | 1,14,898 no. defective consumer meters replaced out of 1,14,898 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 3,467 km renovation of LT line by AB Cable completed out of 3,467 km in scope. | |||||
1,223 no New Distribution Transformer installed out of 1,240 no. in scope. | ||||||
7 | Malda | Feeder Segregation | LOI issued | M/S Bajaj Electricals Ltd. | 23 no Feeders are commissioned out of 26 no. feeders. | December,2021 |
Metering | 1,00,017 no. defective consumer meters replaced out of 1,00,017 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 905 km renovation of LT line by AB Cable completed out of 905 km in scope. | |||||
1,510 no New Distribution Transformer installed out of 1,654 no. in scope. 404 no. augmentation of DTR completed out of 404 no. in scope. | ||||||
8 | Murshidabad | Feeder Segregation | LOA issued | M/S SPML Ltd. | 45 no Feeders are commissioned out of 50 no.
feeders. 312 no New Distribution Transformer installed out of 340 no. in scope. |
March,2021 |
Metering | LOA issued | M/S L&T Ltd. | 1,44,898 no. defective consumer meters replaced out of 1,44,898 no. in scope. | |||
Village Infrastructure for access to power for all Rural HH. | 3,343 km renovation of LT line by AB Cable completed out of 3,343 km in scope. | |||||
338 no New Distribution Transformer installed out of 339 no. in scope. 713 no. augmentation of DTR completed out of 713 no. in scope. | ||||||
9 | Nadia | Feeder Segregation | LOA issued | M/S L&T Ltd. | 33 no Feeders are commissioned out of 33 no. feeders. | Completed |
Metering | 2,04,975 no. defective consumer meters replaced out of 2,04,975 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 3,074 km renovation of LT line by AB Cable completed out of 3,074 km in scope. | |||||
1,114 no New Distribution Transformer installed out of 1,128 no. in scope. 243 no. augmentation of DTR completed out of 243 no. in scope. | ||||||
10 | Paschim Midnapur | Feeder Segregation | LOI Issued | M/S ILFS ECC Ltd. | 53 no Feeders are commissioned out of 68 no.
feeders. 795 no New Distribution Transformer installed out of 1,079 no. in scope. |
December,2021 |
Metering | LOA issued | M/S L&T Ltd. | 1,99,915 no. defective consumer meters replaced out of 1,99,915 no. in scope. | Completed | ||
Village Infrastructure for access to power for all Rural HH. | 3,890 km renovation of LT line by AB Cable completed out of 3,890 km in scope. | |||||
807 no New Distribution Transformer installed out of 807 no. in scope. 1,438 no. augmentation of DTR completed out of 1,438 no. in scope. | ||||||
11 | Purba Midnapur | Feeder Segregation | LOA issued | M/S L&T Ltd. | 10 no Feeders are commissioned out of 10 no. feeders. | Completed |
Metering | 1,89,056 no. defective consumer meters replaced out of 1,89,056 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 2,451 km renovation of LT line by AB Cable completed out of 2,451 km in scope. | |||||
1,633 no New Distribution Transformer installed out of 1,633 no. in scope. | ||||||
12 | Bankura | Feeder Segregation | LOA Issued | M/S L&T Ltd. | 24 no Feeders are commissioned out of 24 no. feeders. | Completed |
Metering | 1,04,510 no. defective consumer meters replaced out of 1,04,510 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 1,664 km renovation of LT line by AB Cable completed out of 1,664 km in scope. | |||||
1,326 no New Distribution Transformer installed out of 1,326 no. in scope. | ||||||
13 | Purulia | Metering | LOA Issued | M/S Montecarlo Ltd. | 75,978 no. defective consumer meters replaced out of 75,978 no. in scope. | Completed |
Village Infrastructure for access to power for all Rural HH. | 1,319 km renovation of LT line by AB Cable completed out of 1,319 km in scope. | |||||
390 no New Distribution Transformer installed out of 390 no. in scope. 42 no. augmentation of DTR completed out of 42 no. in scope. | ||||||
14 | Darjeeling | Metering | Departmental Execution | 25,378 no. defective consumer meters replaced out of 25,378 no. in scope. | December,2021 | |
Village Infrastructure for access to power for all Rural HH. | 682 km renovation of LT line by AB Cable completed out of 682 km in scope. | |||||
304 no New Distribution Transformer installed out of 315 no. in scope. | ||||||
Sansard Adarsh Gram Yojona (SAGY) | Departmental Execution | Work completed. | Completed | |||
15 | Jaipaiguri(including Alipurduar) | Feeder Segregation | LOA issued | M/S L&T Ltd. | 05 no Feeders are commissioned out of 06 no. feeders. | December,2021 |
Metering | 1,37,790 no. defective consumer meters replaced out of 1,37,790 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 1,304 km renovation of LT line by AB Cable completed out of 1,304 km in scope. | |||||
554 no New Distribution Transformer installed out of 557 no. in scope. | ||||||
16 | Coochbehar | Feeder Segregation | LOA issued | M/S L&T Ltd | 04 no Feeders are commissioned out of 04 no. feeders. | Completed |
Metering | 1,16,015 no. defective consumer meters replaced out of 1,16,015 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 1,081 km renovation of LT line by AB Cable completed out of 1,081 km in scope. | |||||
461 no New Distribution Transformer installed out of 461 no. in scope. | ||||||
Electrification of Habitations less than 100 HH. | M/S BISPA India Ltd | Work Completed. | Completed | |||
17 | Uttar Dinajpur | Feeder Segregation | LOA issued | M/S L&T Ltd. | 14 no Feeders are commissioned out of 16 no. feeders. | December,2021 |
Metering | 1,08,243 no. defective consumer meters replaced out of 1,08,243 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 812 km renovation of LT line by AB Cable completed out of 812 km in scope. | |||||
619 no New Distribution Transformer installed out of 642 no. in scope. | ||||||
18 | Dakhin Dinajpur | Feeder Segregation | LOA issued | M/S L&T Ltd. | 17 no Feeders are commissioned out of 18 no. feeders. | December,2021 |
Metering | 96,275 no. defective consumer meters replaced out of 96,275 no. in scope. | |||||
Village Infrastructure for access to power for all Rural HH. | 908 km renovation of LT line by AB Cable completed out of 908 km in scope. | |||||
522 no New Distribution Transformer installed out of 527 no. in scope. 484 no. augmentation of DTR completed out of 484 no. in scope. |
SL NO: | District |
|
|
|||||
---|---|---|---|---|---|---|---|---|
Number | Status of work | Target for completion | Number | Status of Work | Name of Turnkey agency | Target for completion | ||
1 | North 24 parganas | 3 | All Sub-Stations commissioned. | Completed |
|
|||
2 | South 24 parganas and Biddhannagar | 4 | All Sub-Stations commissioned. | Completed | ||||
3 | Howrah | 4 | All Sub-Stations commissioned. | Completed | ||||
4 | Burdwan | 10 | All substations comissioned. | Completed | ||||
5 | Hooghly | 3 | All Substation Comissioned. | Completed | ||||
6 | Birbhum | 3 | All Sub-Stations commissioned. | Completed | 2 | All Sub-stations Comissioned. | M/S Bajaj Electricals Ltd | Completed |
7 | Malda | 5 | All Sub-stations Comissioned | Completed | 3 | All Sub-stations Comissioned | M/S Bajaj Electricals Ltd | Completed |
8 | Murshidabad | 4 | All Sub-Stations commissioned. | Completed | -- | |||
9 | Nadia | 4 | 3 No Substation Comissioned. | Completed | ||||
10 | Purulia | 1 | Sub-Stn Commissioned | Completed | ||||
11 | Paschim Midnapur | 6 | All Sub-Stations Comissioned. | Completed | ||||
12 | Purba Midnapur | 4 | All Sub-Stations commissioned. | Completed | ||||
13 | Bankura | 0 | -- | Completed | 3 | All Substations Comissioned. | M/S Bajaj Electricals Ltd | Completed |
14 | Darjeeling | 2 | All Sub-Stations commissioned. | Completed | 2 | All Substations Comissioned. | M/S Bajaj Electricals Ltd | Completed |
15 | Jaipaiguri (including Alipurduar) | 1 | Sub-Stn Commissioned | Completed | 4 | All Substations Comissioned. | M/S Bajaj Electricals Ltd | Completed |
All Substations Comissioned. | M/S T&T Ltd | Completed | ||||||
16 | Coochbehar | 5 | All Sub-Stations commissioned. | Completed | -- | |||
17 | Uttar Dinajpur | 4 | All Sub-Stations commissioned. | Completed | ||||
18 | Dakhin Dinajpur | 1 | Sub-Stn Commissioned | Completed | 2 | All Substations Comissioned. | M/S T&T Ltd | Completed |
SL NO: | Name of the District | Departmental Execution | |||
---|---|---|---|---|---|
Scope of PTR Augmented (No) | Status of work | Target for completion | |||
1 | North 24 parganas | 7 | 7 | -- | |
2 | South 24 parganas and Biddhannagar | 11 | 11 | -- | |
3 | Howrah | 8 | 8 | -- | |
4 | Burdwan | 11 | 9 | Sept,2021 | |
5 | Hooghly | 5 | 5 | -- | |
6 | Birbhum | 10 | 10 | -- | |
7 | Malda | 5 | 5 | -- | |
8 | Murshidabad | 13 | 13 | -- | |
9 | Nadia | 9 | 9 | -- | |
10 | Purulia | 0 | 0 | -- | |
11 | Paschim Midnapur | 10 | 10 | -- | |
12 | Purba Midnapur | 12 | 11 | Sept,2021 | |
13 | Bankura | 14 | 14 | -- | |
14 | Darjeeling | 7 | 7 | -- | |
15 | Jaipaiguri (including Alipurduar) |
7 | 7 | -- | |
16 | Coochbehar | 6 | 6 | -- | |
17 | Uttar Dinajpur | 8 | 8 | -- | |
18 | Dakhin Dinajpur | 3 | 3 | -- |